Estimated reading time: 9 minutes
For correct cost management in Microsoft Project, it is necessary to associate both the indirect costs that repetitive costs to an activity, with a similar/equal criterion to the real criterion.
This activity must have the particularity of having a dynamic duration that varies from that of the project. That is, if the project lasts less this activity is shortened and vice versa lengthens to lengthen the duration of the project.
Hammock task
In Project Management, a purposeful activity like this comes definita Hammock task
, or Level of Effort
.
In Microsoft Project cost management, a Hammock task
it is an activity that groups other activities, and therefore linked to a start date and an end date. The activities grouped by a Hammock task
they might even be unrelated, in the hierarchical sense of one W.B.S.
, or in the logical sense to the dependence of an activity.
Una Hammock task
groups:
The duration of theHammock task
it can also be set by the sub-activities inside it, so that the abstract grouping has a start date of the first of any of the sub-activities and the end date is the last of the contents.
A Hammock task
is considered a form of summary activity similar to an activity Level of Effort
.
Level of Effort
To support Microsoft Project cost management, let's now see what an activity is and how to implement it Level of Effort
.
A task Level of Effort
it is a support activity that must be carried out to support other work activities or the entire project. It usually consists of short amounts of work that must be repeated periodically. For example the accounting of the project budget, the relationship with the customers or the maintenance of the machinery during production.
Because an activity Level of Effort
it is not in itself a work object directly associated with the realization of the product, service or final result of the project, but a support to work, its duration is based on the duration of the working activity. Precisely for this reason, an activity Level of Effort
it must not be on the critical path of project planning, since it never adds time to the project.
The estimate of a task Level Of Effort
is one of the main tasks of a project manager.
We insert this activity as the first activity of the project plan, and we call it Level of Effort indirect costs, without entering start and end dates, nor duration.
We can assign resources of any kind to this activity with appropriate Assignment Units to spread the costs evenly throughout the project.
Let's see step by step how to do it:
Level Of Effort
indirect costs and select Paste special;Level Of Effort
indirect costs and select Paste special;Once this is done, the duration of the activity Level Of Effort
indirect costs will cover the entire project, in our case from 26 February 2018 to 27 April 2018.
The display of the activity LOE
indirect costs could be misleading, as it is always critical. The GANTT display may be problematic with the activity display LOE
indirect costs, so let's see how to hide it.
To avoid displaying it, we can create a custom type field Mark (true / false), and a display filter to hide the activity LOE
indirect costs.
To create the field Level Of Effort Task
, right click on the "Add New Column" column, and choose "Custom Fields" from the context menu
And create the field Level Of Effort Task
like Mark
At this point we can display a new column by associating the newly created custom field, and set the value of the cell relative to the activity Level Of Effort
indirect costs a Si, as in the figure.
This value will be used by the filter we are going to create to identify the activity we want to hide.
To create the filter, to hide the display of the activity Level Of Effort
indirect costs from the menu Immagine, we identify the drop-down list No filter present in the center of the Ribbon in the group Data.
From the drop-down list of commands we choose Other filters and from this we click on the button New.
Enter the filter name Hide LOE
, we activate the check-box Show in the menu to have the new filter always displayed in the drop-down list of available filters.
The criteria of the new filter are:
Field Name = Level Of Effort Task
Condition = "different from"
Value (s) = "Yes"
Click on View, activate with a mouse click the list of available filters and then click on Hide LOE
,
The activity Level Of Effort
it will be hidden.
To assign resources to this activity, proceed normally. Let's try to assign resources Administration e Sales Manager assigned with a max unit of 50%. In this way, half of the indirect cost of the Project Manager and his company car will be borne by the project.
To attribute the cost of the two resources to this activity during the execution of the project, it is sufficient to enhance the camp % completion with a value proportional to the time elapsed from the beginning of the project to the time the project is updated.
We can have the same result by creating asupport activities to project activities.
An activity Hammock o Level Of Effort it can also refer to a single phase of the project.
We create three activities:
The result will be as in the following figure.
At this point we can assign to the activity of Support all the resources and costs necessary to support the entire project.
If the project (or phase) undergoes a time extension, then the duration of the activity LOE increases and thus costs related to work-type resources or costs charged manually.
Ercole Palmeri
Coveware by Veeam will continue to provide cyber extortion incident response services. Coveware will offer forensics and remediation capabilities…
Predictive maintenance is revolutionizing the oil & gas sector, with an innovative and proactive approach to plant management.…
The UK CMA has issued a warning about Big Tech's behavior in the artificial intelligence market. There…
The "Green Houses" Decree, formulated by the European Union to enhance the energy efficiency of buildings, has concluded its legislative process with…