Tutorial

How to make a massive shift of related tasks in Microsoft Project

The management of a complex project sometimes requires the application of complex and delicate operations. In this Microsoft Project Tutorial we see how to move a large number of tasks, using the native tools of Ms Project

Suppose a large portion of the entire project has slipped, and task start dates need to be changed. If the following tasks are on the Critical Path, no problem. Now let's see how to do it in the Microsoft Project Tutorial. As soon as ms Project moves the activities we select, all the following ones will move respecting also the non-working days of the project calendar. If, on the other hand, the tasks that follow those to be shifted do not belong to the critical path, then we should manually move them
Furthermore, if we change the start date of the activity in the column of the same name to move the start dates Gantt chart, then MS Project will insert the constraint Start not before, as in the following image:

we see the icon indicating the constraint in the first column. If we apply the same method to dozens of activities, in addition to being long and laborious, we load our ms Project plan with constraints.

You might also like: How to monitor the progress of your project with Microsoft Project
You might also like: How to create a new project with Smartsheet, in the Cloud

Let's see below the application of the Move Activity Forward / Back tool. Microsoft project tutorial

Microsoft Project provides a very convenient command, which does practically all the work by itself. Just select the activities we want to move and ms Project will change the start dates of the activities (selected) of the chosen amount of days. To do this we choose the command Move from the menu Activities as shown:

The starting dates of the selected activities have been changed by one week. An unpleasant side effect is that all activities could inherit a constraint Start not earlier than.

The scheduling in example is part of the Critical Path. If this were not the case, we would find ourselves moving the subsequent activities with the command Shift activity.

Innovation newsletter
Don't miss the most important news on innovation. Sign up to receive them by email.

Trying to insert as few constraints as possible is a good practice to be able to manage the update of the ms Project plan more easily

You might also like: Project Management: training for the management of Innovation

For more information on Project Management and Microsoft Project training courses, you can contact me by sending an email to info @bloginnovazione.it, or by filling out the contact form of BlogInnovazione.it

Ercole Palmeri

Temporary Innovation Manager

Innovation newsletter
Don't miss the most important news on innovation. Sign up to receive them by email.

Latest Articles

The Benefits of Coloring Pages for Children - a world of magic for all ages

Developing fine motor skills through coloring prepares children for more complex skills like writing. To color…

May 2, 2024

The Future is Here: How the Shipping Industry is Revolutionizing the Global Economy

The naval sector is a true global economic power, which has navigated towards a 150 billion market...

May 1, 2024

Publishers and OpenAI sign agreements to regulate the flow of information processed by Artificial Intelligence

Last Monday, the Financial Times announced a deal with OpenAI. FT licenses its world-class journalism…

April 30 2024

Online Payments: Here's How Streaming Services Make You Pay Forever

Millions of people pay for streaming services, paying monthly subscription fees. It is common opinion that you…

April 29 2024